EKPC Generating Unit Projects

 

Unit

Fuel

Location

Capacity

Regulatory Approval

Construction Phase

Scheduled Operating Date

Spurlock Unit #4

Coal

Spurlock Station

278 MW

Certificate of Need, final air permit approved & RUS approval obtained.

 

 

Construction has begun

April 2009

Smith

Unit #1

Coal

Smith Station

278 MW

Certificate of Need granted. Ky. air permit & RUS approval pending.

 

 

Not started

2012/2013

Spurlock Unit  #1 Scrubber Spurlock Station Certificate of Need granted. Scrubber air permit approved.

 

Construction has begun Spring 2009
Spurlock Unit #2 Scrubber Spurlock Station Certificate of Need granted. Scrubber air permit approved. Construction has begun October 2008

CT Unit #8

Nat. gas

Smith Station

92 MW summer, 100 MW winter

Ky. air permit currently under review; RUS approval pending.

 

 

Not started

Summer 2009

CT Unit #9

Nat. gas

Smith Station

92 MW summer, 100 MW winter

Ky. air permit currently under review; RUS approval pending.

 

 

Not started

Summer 2009